Cradley Heath Interchange - Stourbridge Line User Group

Go to content
Cradley Heath Interchange Rebuild
On 28 September 2014, Cradley Heath Interchange was closed for a complete reconstruction costing £1.9 million from a Government grant under the Brierley Hill Better Bus Area.

The following photographs show the progress as the old Interchange was demolished and the new one gradually rose in its place.  All photos were taken from approximately the same location.
13 March 2014
2 October 2014
18 November 2014
8 December 2014
5 January 2015
10 February 2015
3 March 2015
30 March 2015
20 April 2015
21 May 2015
16 June 2015
27 July 2015
Latest News

20 October 2020

West Midlands Railway has announced that it will be introducing a temporary timetable from 26 October which will see further reduced services.  Full details may be read in the News and Comment section.

16 October 2020

Stourbridge Junction has narrowly missed out on being named the station of the year in a poll organised by the Rail Delivery Group.  Full details may be read in the News and Comment section.

27 September 2020

A reduced Monday to Friday timetable has been introduced because of the number of services currently being cancelled due to train crew issues.  The temporary timetable can be found on the Timetables page.

26 August 2020

The timetables on the Stourbridge line will be improved from 7 September.   Full details may be read in the News and Comment section.

7 August 2020

Improvement works will shortly take place at Hartlebury.  The programme of works will include the extension of both platforms to accommodate the new four-car Class 196 trains, as well as the refurbishment of existing platforms.  The work is scheduled for completion in February 2021.

23 July 2020

The first of the new Class 196 units was out on the Stourbridge line today when it made its first ever test run from Tyseley to Hereford and back.

7 June 2020

The new station building at Kidderminster has been opened.
Full details may be read in the News and Comment section.

23 May 2020

The 10 successful projects from the bids submitted in the first round under the Restore Your railways scheme have been announced by the Secretary of State for Transport, Grant Shapps.  A scheme submitted by PMOL for a light rail link between Stourbridge Junction and Brierley Hill was not among the 10 successful bids but PMOL has been asked to provide further details to a subsequent round.
The Membership Secretary
Stourbridge Line User Group
46 Sandringham Road
Wordsley
Stourbridge
West Midlands
DY8 5HL


Site Last Updated on 25 October 2020
(Timetables)
The Membership Secretary
Stourbridge Line User Group
46 Sandringham Road
Wordsley
Stourbridge
West Midlands
DY8 5HL

Back to content